THE LAST PLANNER SYSTEM OF PRODUCTION CONTROL
by
HERMAN GLENN BALLARD
A thesis submitted to the Faculty of Engineering
of The University of Birmingham
for the degree of
DOCTOR OF PHILOSOPHY
School of Civil Engineer
ing
Faculty of Engineering
The University of Birmingham
May 2000
ACKNOWLEDGEMENTS
Many individuals and companies contributed to this research. To name a few:
q
David Seymour, my thesis advisor
q
Anne Seymour, for giving me a home in Birmingham
q
David
Hoare and Peter
Deasley, thesis examiners
q
Greg Howell, business partner and co-thinker
q
Lauri
Koskela, for his example and inspiration
q
Todd
Zabelle and the Pacific Contracting team for their willingness to try new
ideas
q
Leo
Linbeck III, Ed Beck and Kathy Jones of
Linbeck Construction for sharing
opportunity and data (3 of the 5 cases were
Linbeck projects)
q
Norm Barnes and the Barnes Construction team for access to projects
q
Iris
Tommelein, external thesis advisor and colleague at UC Berkeley
q
Jeanne Ballard, my wife, for putting up with me, especially my absences from
home
ABSTRACT
Project controls have traditionally been focused on after-the-fact detection of variances.
This thesis proposes a control system, the Last Planner
system, that causes the
realization of plans, and thus supplements project management's concern for management
of contracts with the management of production.
The Last Planner system has previously been successively applied by firms with direct
responsibility for production management; e.g.,
speciality contractors. This thesis
extends system application to those coordinating specialists, both in design and
construction, through a series of case studies, one of which also explores the limits on
unilateral implementation by specialists.
In addition to the extended application, two questions drive this research. The first
question is 1)
What can be done by way of tools provided and improved implementation
of the Last Planner system of production control to increase plan reliability above the
70% PPC level?
Previous research revealed substantial improvement in productivity for
those who improved plan reliability to the 70% level, consequently there is reason to
hope for further improvement, possibly in all performance dimensions, especially with
application across an entire project rather than limited to individual
speciality firms. That
question is explored in three case studies, the last of which achieves the 90% target.
The second research question is
2) How/Can Last Planner be successfully applied to
increase plan reliability during design processes
1
?
That question is explored in an
extensive case study, which significantly contributes to understanding the design process
from the perspective of active control, but unfortunately does not fully answer the
question, primarily because the project was aborted prior to start of construction.
However, it is argued that the Last Planner system is especially appropriate for design
production control because of the value-generating nature
No comments:
Post a Comment